MDP 26-04 City of Turlock CP 24-045 “Well 36 GAC Treatment"
Summary
SCH Number
2026050775
Lead Agency
City of Turlock
Document Title
MDP 26-04 City of Turlock CP 24-045 “Well 36 GAC Treatment"
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
Land Use - Park
Zone/District - Low Density Residential
Document Description
Project Background
Well 36 is located within Summerfaire Park located at 1350 N. Fulkerth Road. Well 36 was constructed in the year 2000. The existing well is currently offline, with plans in place to replace the pump and motor before the proposed Granular Activated Carbon (GAC) treatment comes online. In the past, the well produced approximately 2,000 gallons per minute (gpm) of groundwater which is used as potable water. Chlorination facilities were added to Well 36 in 2022. 1,2,3-Trichloropropane (TCP) has been consistently detected at levels that exceed the maximum contaminant level (MCL) of 5 parts per trillion and the City received a compliance order from the Division of Drinking Water in 2023. Arsenic concentrations have been trending upward and are approaching the MCL of 10 parts per billion (ppb). The well includes a pump discharge header equipped with two (2) blind flanged tees separated by an isolated gate valve.
Project Description
The City proposes implementing a GAC filtration system to remove TCP from Well 36 and construct future arsenic treatment facilities. Well 36 is located in the southeast corner of Summerfaire Park, adjacent to N. Soderquist Road. The well has a production capacity of approximately 2 ,000 gpm. The proposed treatment site partially extends into the existing detention basin to accommodate future arsenic infrastructure. The area of potential effect surveyed for biological and cultural resources is approximately 1.0 acres.
The major components of the GAC Project include:
• Removal of 15 trees
• Placement of approximately 6,000 cubic yards of fill within the existing detention basin
• Installation of new security fencing and perimeter security landscaping utilizing thorned plant species (rose bushes, Pyracantha)
• Perimeter landscaping on all four (4) sides of the facility
• Construction of two (2) commercial-grade drive approaches and a 40-foot-wide half circle access road
• Aggregate surfacing
• Installation of six (6) 12-foot diameter GAC treatment vessels
• Ductile iron process piping, primarily 12 -inch and diameters
The major components for the future arsenic treatment include:
• Installation of three (3) 12-foot diameter filter vessels
• Construction of an approximately 20-foot diameter washwater equalization basin
• Installation of a 35-foot by 60-foot chemical storage enclosure
• Installation of ductile iron and high-density polyethylene (HDPE) piping
Site runoff and backwash water would discharge to the basin drop inlet. The existing storm drain pipeline located in the southern portion of the site would be intercepted and rerouted to avoid future conflicts with the future arsenic treatment plant.
Compliance with the City of Turlock Development Services
Building Division
The proposed Project would comply with the California Building Code and the Turlock Municipal Code (TMC) in effect at the time of building permit application. A separate permit for any site lighting would be obtained if needed.
Fire Department
The proposed Project shall comply with the current California Fire Code, National Fire Code (NFPA), California Mechanical Code, and the Turlock Municipal Code in effect at the time of building permit application. Electrical disconnect shall be accessible from the exterior of the building or in a secure electrical room that opens directly to the outside. Disconnect or electrical room will be identified with an approved all weather sign. Fire line requirements shall be met. As well as, fire lanes shall be painted throughout the proposed project.
The following permanent all-weather signage shall be installed at minimum of three-inch letters/numbers:
• MAIN ELECTRICAL DISCONNECT
• MAIN GAS SHUT OFF
• FIRE CONTROL ROOM
• FDC (address numerals)
• ELECTRICAL ROOM
• HVAC units shall be numbered (coordinating with breakers and fire alarm system)
Municipal Services – Water
Prior to issuance of a building permit, water and sewer utilities shall be reviewed and approved by Municipal Services.
Compliance with the San Joaquin Valley Air Pollution Control District
In accordance with San Joaquin Valley Air Pollution Control District (SJVAPCD) Rule 2010 an Authority to Construct and Permit to Operate are required. Prior to construction, the Project proponent should submit to the SJVAPCD an application for an ATC. Additionally, the Project shall comply with SJVAPCD Rule 2201 that requires that new and modified stationary sources of emissions mitigate their emissions using Best Available Control Technology. The Project shall comply with SJVAPCD Rule 4601 for architectural coatings if applicable. A prioritization health risk assessment should be performed in coordination with SJVAPCD.
Minor Discretionary Permit
In accordance with TMC 9-3-202 design review through a Minor Discretionary Permit is required for the tanks and on-site structures associated with this Project.
Construction Schedule
GAC TREATMENT FACILITIES
Construction start: Fall of 2026
Construction end: Summer/Fall of 2027
Duration: approximately 12 months
ARSENIC TREATMENT PLANT
Construction dates: unknown at this time.
Duration: approximately 12 months
Equipment:
Equipment would likely include excavators, bulldozers, skidsteers, dump trucks, loaders, concrete pump truck, graders, water truck, etc.
Operation and Maintenance
Existing city staff would provide any maintenance necessary for the water treatment facilities at the Well 36 site.
Contact Information
Name
Katie Quintero
Agency Name
City of Turlock
Job Title
Planning Manager
Contact Types
Lead/Public Agency / Project Applicant
Phone
Email
Name
Stephen Fremming
Agency Name
City of Turlock
Job Title
Principal Civil Engineer
Contact Types
Lead/Public Agency / Project Applicant
Phone
Email
Name
Briza Grace Sholars
Agency Name
Provost & Pritchard Consulting Group
Job Title
Principal Environmental Planner
Contact Types
Consulting Firm
Address
Phone
Email
Location
Coordinates
Cities
Turlock
Counties
Stanislaus
Regions
Citywide
Cross Streets
southeast corner of Summerfaire Park, adjacent to N. Soderquist Road
Zip
95380
Total Acres
1.0
Parcel #
042-001-008
State Highways
99
Railways
Union Pacific
Schools
Osborn Two-way Immersion Academy
Waterways
Upper Lateral Number Four
Township
05S
Range
10E
Section
15
Base
MDMB
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Air Resources Board (ARB), California Department of Fish and Wildlife, Central Region 4 (CDFW), California Department of Fish and Wildlife, North Central Region 2 (CDFW), California Department of Forestry and Fire Protection (CAL FIRE), California Department of Parks and Recreation, California Department of Toxic Substances Control (DTSC), California Department of Transportation, District 10 (DOT), California Department of Transportation, Division of Aeronautics (DOT), California Department of Transportation, Division of Transportation Planning (DOT), California Department of Water Resources (DWR), California Fish and Game Commission (CDFGC), California Highway Patrol (CHP), California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB), Central Valley Flood Protection Board, Office of Historic Preservation, State Water Resources Control Board, Division of Drinking Water, State Water Resources Control Board, Division of Drinking Water, District 10, State Water Resources Control Board, Division of Water Rights, State Water Resources Control Board, Divison of Financial Assistance
Development Types
Other (Water Treatment Project at Well 36 site)
Local Actions
Water Treatment Project
Project Issues
Biological Resources, Cultural Resources, Tribal Cultural Resources
Public Review Period Start
Public Review Period End
Attachments
Draft Environmental Document [Draft IS, NOI_NOA_Public notices, OPR Summary Form, Appx,]
Notice of Completion [NOC] Transmittal form
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.