B2 Reservoir Project
2 Documents in Project
Summary
SCH Number
2025081340
Lead Agency
Marina Coast Water District
Document Title
B2 Reservoir Project
Document Type
NOD - Notice of Determination
Received
Posted
10/23/2025
Document Description
The proposed project involves construction of a new 2.16-million-gallon potable water reservoir (B2) adjacent to the existing B1 reservoir to meet current and future demands of the Ord Community as identified in MCWD’s 2020 Master Plan. The project also includes associated site and infrastructure improvements. The B2 reservoir would connect to the existing B1 transmission main through approximately 270 feet of 20-inch pipeline. Site improvements include a paved access road and driveway connection to Colonel Durham Street, a 90-foot retaining wall, a percolation basin, 8-foot perimeter fencing, and a 12-foot swing gate. At the B1 reservoir yard, improvements include relocating the booster pump station, upgrading electrical panels, adding an emergency generator, replacing inlet/outlet valves, and removing fencing between the yards to create one contiguous facility. Activities are expected to begin in 2025 and last 18 months, with weekday work hours.
Contact Information
Name
Jack Gao
Agency Name
Marina Coast Water District
Job Title
Senior Project Manager
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project
Phone
Email
Location
Coordinates
Cities
Seaside
Counties
Monterey
Regions
Citywide
Cross Streets
Colonel Durham St and 6th Ave
Zip
93933
Total Acres
2.9 acres
Parcel #
031-261-002-000
State Highways
State Route 1
Railways
N/A
Airports
Marina Municipal
Schools
CSU Monterey Bay
Waterways
Monterey Bay, Salinas River
Other Location Info
Project is located in the City of Seaside and on the California State University Monterey Bay campus.
Notice of Determination
Approving Agency
Marina Coast Water District
Approving Agency Role
Lead Agency
Approved On
County Clerk
Monterey
Final Environmental Document Available at
920 2nd Avenue, Suite A, Marina, CA 93933
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Final Document(s) [Approved_Certified draft environmental documents]
Notice of Determination
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.