Lockhart Solar (PROJ-2022-00066)

2 Documents in Project

Summary

SCH Number
2025030468
Lead Agency
San Bernardino County
Document Title
Lockhart Solar (PROJ-2022-00066)
Document Type
NOD - Notice of Determination
Received
Posted
7/31/2025
Document Description
A Conditional Use Permi1 (CUP} 1o cons1ruct and operate 1wo 4-Megawat solar photovoltaic (PV) power generating facili1ies with battery storage capabilities on 75 acres located northwest of the unincorporated community of Hinkley (the Project). The Project would generate electricity using solar PV modules mounted on single-axis trackers end arranged in north-south arrays across the Project Site. The system would store electrical production in long-duration batteries. Switchgear, a weather station, inverters, and transformers would manage the system and convert power for distribution to the nearby transmission grid. Electrical conduit, transmission and collection lines would be installed bo1h overhead and underground. The solar PV facilities would in1erconnec1 to the 33kV distribution line owned and operated by Southern California Edison (SCE).

Contact Information

Name
Delanie Garlick
Agency Name
San Bernardino County Land Use Services
Job Title
Planner
Contact Types
Lead/Public Agency

Name
K. Mcdaniels
Agency Name
Juniper Energy, LLC
Job Title
Applicant
Contact Types
Project Applicant

Location

Cities
phelan
Counties
San Bernardino
Regions
Citywide, Countywide, Southern California, Unincorporated
Parcel #
0490171010000
Other Location Info
315 Roy Rd

Notice of Determination

Approving Agency
San Bernardino County
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Bernardino
Final Environmental Document Available at
385 North Arrowhead Avenue, First Floor, San Bernardino, CA 92415-0187

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.

Download CSV New Search Print