Conditional Use Permit #23-0020, Conditional Use Permit #23-0021 and Conditional Use Permit #23-0022

5 Documents in Project

Summary

SCH Number
2024010510
Lead Agency
Imperial County
Document Title
Conditional Use Permit #23-0020, Conditional Use Permit #23-0021 and Conditional Use Permit #23-0022
Document Type
NOD - Notice of Determination
Received
Posted
8/7/2025
Document Description
The applicant, proposes the construction and operation of three facilities CUP#23- 0020 is to develop a geothermal plant and solar energy facility; a 7-megawatt (MW) parasitic solar facility, underground distribution line, and a project substation. CUP#23-0021 is to develop a 15MW solar energy facility that will provide a parasitic load to the existing Heber 2 geothermal power plant. CUP #23-0022 is to develop up to three geothermal production wells, one geothermal injection well, and approximately 4,500 linear feet of new brine pipelines.

Contact Information

Name
Jim Minnick
Agency Name
Imperial County Planning & Development
Job Title
Director
Contact Types
Lead/Public Agency

Name
OrHeber 3, LLC, Heber Field Company, LLC
Agency Name
Imperial County Planning & Development
Job Title
Director
Contact Types
Project Applicant

Name
The Second Imperial Geothermal Company
Agency Name
Imperial County Planning & Development
Job Title
Director
Contact Types
Project Applicant

Location

Cities
Heber
Counties
Imperial
Regions
Countywide
Zip
92249
Other Information
855, 853 & 602 Dogwood Road. Heber, CA 92249, Imperial County

Notice of Determination

Approving Agency
Imperial County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On
County Clerk
Imperial
Final Environmental Document Available at
Imperial County Planning & Development Services, 801 Main Street. El Centro, CA 92243

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.

Download CSV New Search Print