SCH Number 2026070823
Project Info
- Title
- Manhole, Gravity Interceptor, and Easement Road Improvements Phase 2 Project
- Description
- The project includes, but is not limited to, rehabilitating or replacing 53 manholes along the Shore Acres Interceptor (SAI) and Willow Pass Interceptor (WPI), rehabilitating existing reinforced concrete pipe (RCP) sewer along the WPI, rehabilitating existing 30-inch vitrified clay pipe (VCP) sewer along the SAI, installing new 30-inch and 12-inch high-density polyethylene (HDPE) sewer pipe, constructing four new manholes, and constructing gravel access roads for maintenance access to District manholes along the SAI.
1 documents in project
| Type | Lead/Public Agency | Received | Title |
|---|---|---|---|
| MND | Delta Diablo Sanitation District | Manhole, Gravity Interceptor, and Easement Road Improvements Phase 2 Project |