Title
Roadhouse Energy Storage Project
Description
Roadhouse Energy Storage, LLC (Applicant), a wholly-owned indirect subsidiary of NextEra Energy Resources, proposes to construct, operate, and ultimately decommission the Roadhouse Energy Storage Project. The Project would consist of a BESS facility with a capacity of up-to 300-megawatts (MW) a 220 kilovolt (kV) collector substation, and an approximately 600-foot generation transmission line (gen-tie line) to connect the BESS to the SCE Mira Loma Substation. The Project site also includes the use of an off-site temporary outdoor staging, construction and vehicle storage yard located at 8254 East Chino Avenue.
Download CSV New Search

 

3 documents in project

Type Lead/Public Agency Received Title
City of Ontario Roadhouse Energy Storage Project
City of Ontario Rich-Haven Specific Plan, 2022 Amendment Project (File No. PSPA22-001)
City of Ontario Rich-Haven Specific Plan Amendment (File No. PSPA22-001)