Mokelumne River Fish Hatchery Electrical Retrofit Project

Summary

SCH Number
2026110382
Public Agency
East Bay Municipal Utility District (EBMUD)
Document Title
Mokelumne River Fish Hatchery Electrical Retrofit Project
Document Type
NOE - Notice of Exemption
Received
Posted
11/13/2026
Document Description
This project is for the replacement of an existing emergency diesel generator that is nearing the end of its service life with a new Tier 4 Final emergency diesel generator at the Mokelumne River Fish Hatchery. The hatchery is located at the end of PG&E's power line, which has led to outages, thereby necessitating reliable backup power to maintain operations to prevent lost fish production. The new generator will be sited on the current location of the existing generator to be removed. Overview and Background The Mokelumne River Fish Hatchery (MRFH) supports the maintenance and enhancement of Chinook salmon and steelhead populations in the Mokelumne River. During unplanned utility power outages, emergency generators provide backup power to critical hatchery equipment, including chillers used to maintain optimal temperatures for egg incubation. East Bay Municipal Utility District (EBMUD) is replacing outdated electrical equipment at the MRFH to improve the reliability of emergency backup power essential to hatchery operations. Power outages that disrupt critical hatchery functions could result in fish production losses and potential regulatory noncompliance. The Project will replace an existing 125 kW emergency generator with a new 500 kW diesel generator certified to meet U.S. Environmental Protection Agency (EPA) Tier 4 Final emissions standards. The new generator will be capable of supplying emergency power to all electrical loads serving the hatchery facility. The Project is located at the MRFH in Clements, San Joaquin County, California (see Figure 1). Project Purpose and Objectives The purpose of the Project is to replace an existing emergency diesel generator, which is nearing the end of its service life, with a new 500 kW diesel generator that meets EPA Tier 4 Final emissions standards and applicable requirements of the San Joaquin Valley Air Pollution Control District (SNAPCD). The Project also includes replacement of associated electrical equipment (e.g., switchboard, automatic transfer switch, control panel, load bank, cables) to ensure the reliability and functionality of the hatchery's emergency power system. Project Location The Project site is located off North McIntire Road in Clements, California (see Figure 1) and is wholly within the MRFH facility site. All Project activities will occur within the existing hatchery facility. The existing access road will be used for construction personnel, equipment, and material deliveries. Project Characteristics The new emergency generator will be installed at the location of an existing emergency diesel generator. During a utility power outage, the automatic transfer switch (A TS) will coordinate with the generator control system to transfer the designated facility electrical loads from utility power to emergency generator power. A second 250 kW emergency diesel generator that serves the York chiller will remain in service as redundancy to the new generator. Project activities will include demolition and removal of the existing 150 kW generator, switchboard/control panel assembly, and associated concrete pad; site preparation; grading and excavation for construction of a new reinforced concrete pad; installation of the new generator and associated electrical equipment; shallow trenching for fiber optic cable installation; and associated paving and site restoration. The proposed Project site plan is shown in Figure 2. Permits and Approvals All Project activities will occur on EBMUD property. Encroachment permits are not required because no work will occur within the public right-of-way. Coordination with PG&E for replacement of a 1200A Panel and transfer of an existing meter will occur. The Project will obtain the applicable air quality permits from the SJV APCD, including the required Authority to Construct and Authority to Operate approvals for the new generator. Schedule and Work Hours The construction schedule will be coordinated with hatchery operations to minimize disruption to critical facility functions. Construction is anticipated to begin in June 2027 and take approximately four months to complete, during the months when the hatchery is not in operation. Construction activities will generally be limited to weekday daytime hours, between 7:00 a.m. and 7 :00 p.m., to the extent feasible. EBMUD Practices and Procedures Standard EBMUD construction environmental protection and safety practices applicable to all EBMUD construction projects have been incorporated into the Project. These standard practices minimize potential environmental effects, protect health and safety, and reduce disruptions associated with construction activities. See Figures 1 and 2 for additional information.

Contact Information

Name
Warren Yee
Agency Name
East Bay Municipal Utility District
Job Title
Assistant Engineer
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project

Location

Cities
Clements
Counties
San Joaquin
Regions
Northern California, Unincorporated
Cross Streets
N. McIntire / Baker Road in Clements
Zip
95227
Total Acres
6
Parcel #
02301001
State Highways
12, 88
Railways
N/A
Airports
N/A
Schools
N/A
Waterways
Murphy Creek, Mokelumne River
Township
T04N
Range
R09E
Section
6
Base
Clements
Other Location Info
Project Location: 25800 N. Mcintire Rd., Clements, San Joaquin County
Other Information
N/A

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
15302
Reasons for Exemption
The Project is exempt under Guideline 15302, because it involves the replacement of existing facilities where the new facility will be located on the same site as the facility replaced and will have substantially the same purpose and capacity as the facilities replaced. The Project will have no significant environmental effects relative to location, cumulative impact, or significant effects due to unusual circumstances, hazardous waste, or historical resources, pursuant to Section 15300.2 of the CEQA Guidelines.
County Clerk
San Joaquin

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.

Download CSV New Search Print