Old Garden at Patricia Emergency Repair - 2090742-14
Summary
SCH Number
2026110157
Public Agency
City of San Luis Obispo
Document Title
Old Garden at Patricia Emergency Repair - 2090742-14
Document Type
NOE - Notice of Exemption
Received
Posted
11/4/2026
Document Description
Emergency repair of a failing culvert along Patricia Drive that is impacting the roadway, a school and City bus route,
causing sinking pavement and bypass around the constructed facilities, and imminent damage to essential public
services, including Patricia Drive and the associated utilities (water, sewer later, natural gas and communication lines)
buried in the crossing. This repair will involve removal of the existing culvert, installation of a new precast concrete culvert,
and reconstruction of the roadway above. This project will protect the roadway, creek and adjacent neighborhoods from
flooding in future storms. Emergency declared on 7/17/2026 per the attached. The proposed emergency project includes
best management practices and measures that will both mitigate the existing hazard and protect water quality (refer to
attached).
Contact Information
Name
Shawna Scott
Agency Name
City of San Luis Obiso
Job Title
Assistant Director of Utilities
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project
Phone
Email
Name
Wyatt Banker-Hix
Agency Name
City of San Luis Obispo
Job Title
Supervising Engineer
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project
Phone
Email
Location
Cities
San Luis Obispo
Counties
San Luis Obispo
Regions
Northern California
Cross Streets
Patricia Drive
Zip
93401
State Highways
1, 101
Railways
UPRR
Waterways
Old Garden Creek and tributaries, Stennner and SLO Creek and tributaries
Other Location Info
City of San Luis Obispo, 266 Patricia Drive
Notice of Exemption
Exempt Status
Emergency Project
Type, Section or Code
Sec. 21080(b)(4); 15269(b)(c)
Reasons for Exemption
Pursuant to California Code of Regulations Title 14, Division 6, Chapter 3, Article 18, Section 15269 - Emergency
Projects, the following emergency projects are exempt from the requirements of CEQA:
b) Emergency repairs to publicly or privately owned service facilities necessary to maintain service essential to the public
health, safety or welfare. Emergency repairs include those that require a reasonable amount of planning to address an
anticipated emergency.
This project was recognized as having a high chance of failure in the short term, which would damage essential public
services, including Patricia Drive and the associated utilities (water, sewer later, natural gas and communication lines)
buried in the crossing. If these facilities were damaged, the public would have limited access to their properties, and
limited ability to use water or natural gas.
(c) Specific actions necessary to prevent or mitigate an emergency. This does not include long-term projects undertaken
for the purpose of preventing or mitigating a situation that has a low probability of occurrence in the short-term, but this
exclusion does not apply (i) if the anticipated period of time to conduct an environmental review of such a long-term
project would create a risk to public health, safety or welfare, or (ii) if activities (such as fire or catastrophic risk mitigation or modifications to improve facility integrity) are proposed for existing facilities in response to an emergency at a similar
existing facility.
The culvert is failing and causing sinking pavement and bypass around the constructed facilities. Construction of this
project will prevent expected failure, which is anticipated to occur during the winter season with heightened rainfall
associated with an El Nino event. Further failure of the culvert will a blockage into the creek and roadway closure, which
would release additional sediment into the creek and require a more extensive repair, or multiple temporary repairs, all of
which would further impact the water quality of Old Garden Creek more significantly than the project as described above.
Measures to protect habitat and water quality within Old Garden Creek, as established by the regulatory agencies with the
receipt of permits, will be incorporated into the project. This will include the following to ensure the restoration of affected
areas:
Implementation of Geotechnical Design Features. A registered geotechnical engineer will be on site inspecting work
and performing other special inspections such as rebar placement and concrete mixes. The geotechnical engineer will
observe grading, backfilling and final wall alignment.
Noise-Reducing Best Management Practices. For the entire duration of the construction phase of the project, the following
practices will be adhered too – use of noise control devices such as mufflers, limited use of pneaumatic tools and a
complaints process through the Public Works Department.
Equipment Idling Restrictions. Throughout the construction phase of the project, the project proponent/contractor shall
implement the following idling restrictions to minimize impacts to sensitive receptors. These idling restrictions shall
be enforced by the Public Works Department.
Biological Resources:
Worker Environmental Awareness Program. Prior to initiation of construction activities (including staging and
mobilization), all personnel associated with Project construction shall attend Worker Environmental Awareness
Program (WEAP) training, conducted by a qualified biologist.
Best Management Practices to Protect Water Quality. All vehicles and equipment shall be in good working condition
and checked daily for leaks. Work during times of precipitation shall be avoided to the maximum extent possible.
The City or their contractor(s) or representative(s) shall utilize Best Management Practices (BMPs), including (but
not limited to): berms, burlap-wrapped fiber rolls, jute netting, sand/gravel bags, and straw bale barriers to stabilize
work areas and prevent any sediment or pollutants from entering the creek.
Preconstruction Survey for Special-Status Plant Species. A preconstruction survey for special-status plant species
shall be conducted by a qualified botanist within the Project Site prior to any site disturbance. If any special-status
plant species, are observed within the Project Site, the location(s) of individual plants or group(s) of plants shall be
clearly flagged by the qualified botanist and avoided during Project construction.
Avoidance and Minimization Measures for Pacific Lamprey. No project activities shall occur in flowing or standing
water within Old Garden Creek, with the exception of the installation and removal of the temporary creek diversion.
Capture and relocation surveys for Pacific lamprey shall be conducted by qualified biologists prior to the
commencement of diversion construction, as well as during dewatering of the work areas.
Steelhead Capture and Relocation: No Project activities shall occur in flowing or standing water in Old Garden
Creek, with the exception of the installation and removal of the temporary creek diversion. Project activities within
the Old Garden Creek channel are proposed to occur between June 1 and October 30, outside of the steelhead
migration season. Block nets shall remain in place until the diversion is functional, at which time the downstream
and upstream block nets shall be removed. Non-native fishes and invertebrates shall be removed from the creek
by qualified biologists.
A qualified biological monitor shall be on-site full-time during all Project activities that involve creek dewatering
and/or the installation or removal of surface water diversions. Once the work area is completely blocked from the
creek and dewatered, and if work conditions and/or prolonged Project activities are conducted outside of the active
Old Garden Creek channel, the monitor shall be on site for no less than two days per week.
Avoidance and Minimization Measures for California Red-legged Frog. A qualified biologist shall survey the Project
Site no more than 48 hours before the onset of work activities. If the biologist finds any life stage of the California
red-legged frog and these individuals are likely to be killed or injured by work activities, the biologist shall be allowed
sufficient time to relocate them from the Project Site before work begins. To ensure that diseases are not conveyed
between sites, the qualified biologist, shall follow the fieldwork code of practice developed by the Declining
Amphibian Populations Task Force at all times.
Preconstruction Survey for Special-Status Birds and Other Nesting Birds. A preconstruction nesting bird survey
shall be conducted by a qualified biologist no more than 14 days prior to initiation of Project activities.
All Project personnel shall be notified as to the existence of the buffer zones and to avoid entering buffer zones
during the nesting season. No Project activities shall occur within the buffer until the avian biologist has confirmed
that breeding/nesting is complete, and the young have fledged the nest. Encroachment into the buffer shall occur
only at the discretion of the qualified biologist.
On-site Biological Monitoring. A qualified biologist shall be on-site during all vegetation removal, initial ground
disturbing activities, and/or during any construction activities that may impact sensitive biological resources, such
as dewatering and diversion installation or removal. The biologist shall have the authority to temporarily halt or
redirect work to avoid impacts to special-status species or other protected biological resources. Once the diversion
has been installed and vegetation removal and initial ground-disturbing activities have been completed, the
biological monitor shall be on-site for no less than two days per week, for a minimum two-hour period per day.
Habitat Mitigation and Monitoring Plan. Project impacts to habitat within the Old Garden Creek corridor shall be
mitigated through implementation of a Habitat Mitigation and Monitoring Plan (HMMP). The HMMP shall be
prepared by a qualified biologist/restoration ecologist. The HMMP shall include details on the restoration of portions
of Old Garden Creek that will be disturbed by the Project, including jurisdictional features, sensitive natural
communities, and associated riparian and stream habitats.
Compensatory actions shall occur on-site and/or off-site using regionally collected native plant material at a
minimum ratio of 1:1 (habitat created to habitat impacted) as directed by a qualified biologist. Note the resource
agencies may require a higher mitigation ratio and, if so, their requirements would prevail. The City is committed to
addressing all temporary and permanent impacts in full upon project completion. Final mitigation ratios required by
the regulatory agencies during the emergency permitting process may differ but shall be confirmed upon the project
completion.
At a minimum, the HMMP shall include the following:
? A description of the jurisdictional waters, sensitive plant communities, riparian and stream habitat, and/or
sensitive plant species disturbed by the project, and how the mitigation method (e.g., restoration, invasive
species removal, enhancement) will achieve the necessary mitigation goal/s;
? a plant palette and methods of salvaging, propagating, seeding, and/or planting the site to be restored;
? a schedule for restoration activities including weed abatement, propagating and planting, soil preparation,
erosion control, qualitative and quantitative monitoring, and reporting;
? identification measurable performance standards for each objective to evaluate the success of the
compensatory mitigation;
? maintenance and monitoring necessary to confirm the mitigation area meets the success criteria; and
? Identification of contingency and adaptive management measures to address unforeseen changes in site
conditions or other components of the mitigation project.
Cultural Resources:
Worker Environmental Awareness Program. A qualified archaeologist shall conduct a Worker Environmental
Awareness Program training on archaeological sensitivity for all construction personnel prior to the commencement
of the project. The training shall be developed by an archaeologist and include a description of the types of cultural
materials that may be encountered, cultural sensitivity issues, regulatory issues, and the proper protocol for
treatment of the materials in the event of a find.
Archaeological Monitoring. Construction-related ground disturbances shall be monitored by a qualified
archaeologist. A Construction Monitoring Treatment Plan shall be approved by the City and implemented during
construction, which will include archaeological monitoring, procedures should an unanticipated discovery occur,
and coordination with Native American Tribes if suspected tribal resources are discovered. Any discoveries will be
summarized in a project completion report.
County Clerk
San Luis Obispo
Attachments
Notice of Exemption
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.