Little Lake Mobile Home Park Water System Improvements: North Main Street Pipeline Extension Project
Summary
SCH Number
2026100691
Lead Agency
City of Willits
Document Title
Little Lake Mobile Home Park Water System Improvements: North Main Street Pipeline Extension Project
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
County road right of way
Document Description
Project Description
A pipeline extension to serve the LLMHP would require the installation of approximately 1.1 miles of up to eight-inch pipeline along N Main Street. N Main Street used to be the main route of Highway 101 before a Highway 101 bypass was constructed around the City. Since the completion of the Highway 101 bypass, much of the N Main Street right-of-way (ROW) has been transferred to the County, and N Main Street is now primarily a County maintained roadway. However, the bridge over Upp Creek and a portion of the road to the south of the bridge is still maintained by the California Department of Transportation. The new pipeline would need to cross Upp Creek by connecting to the existing roadway bridge, which is located between the City limits and the LLMHP, or by jack and bore under Upp Creek. An access route at the intersection of North Main Street south of the bridge would be a part of the APE as well as an extended area east of the road to allow for jack and bore. It is anticipated that the majority of the pipeline would be under the roadway pavement or right off the shoulder of the roadway (between three to five feet from the edge of the pavement). Either open-cut or trenchless installation methods would be used for pipe installation. For segments of the pipeline that would require open-cut installation, this would require the cutting and rehabilitation of the pavement.
Pressures at the connection point are anticipated to be around 60 pounds per square inch (psi). The proposed LLMHP meter location is approximately 40 feet lower in elevation than the connection point to the City system, and it is anticipated that the City could deliver water to the LLMHP at pressures in the range of 60 psi to 80 psi without the need for a booster pump. The highest residential lot within the LLMHP is approximately 100 feet higher than the proposed City meter location.
In order to connect the LLMHP system to the City, the proposed Project is anticipated to involve the following project components:
• Approximately 6,000 feet of up to eight-inch polyvinyl chloride (PVC) pipe
installed along/within N Main Street;
• Connection to existing 10-inch City water main;
• Up to eight-inch gate valve assemblies;
• Up to four-inch City meter and backflow prevention device at LLMHP property
entrance;
• Attachment of pipeline to existing Upp Creek bridge;
• Three fire hydrants; and
• Minor onsite LLMHP distribution system modifications to connect system to new
City meter.
Construction Schedule
Excavation during construction would generate spoils would be used as backfill ideally or, if necessary, hauled off-site to approved City or County locations. For all excavation in roadway areas, once filled and compacted, the roadways would be resurfaced to County standards. Excavations in bare ground areas would be resurfaced with hardscape (pavement or concrete) or revegetated with native grasses indigenous to the disturbed area or landscaped in accordance with County-approved building permit plans. The pipe installation would be within the existing road ROW, and accessibility and staging would be on the roadway; single-lane traffic control would be required and coordinated with the County during construction.
Construction of the proposed Project could require various equipment including, but not limited to, excavators, backhoes, front-end loaders, skid loader, compactors, double transfer trucks for soil hauling, concrete trucks, concrete/industrial saws, rollers, and paving equipment. Equipment and staging areas for the construction activities would be stationed along the stretch of pipeline within County ROW or, for the sake of the on-site distribution improvements, within LLMHP-owned property. Construction activities would generally be limited to weekdays from 7 a.m. to 5 p.m. Nighttime construction is not expected to be necessary.
Project construction would involve the storage, use, and transport of small amounts of hazardous materials (e.g., asphalt, fuel, lubricants, and other substances) on roadways. Regulations governing hazardous materials transport are stated in Title 22 California Code of Regulations (CCR) and the California Vehicle Code (Title 13 CCR). The timing of the completed design and construction of the proposed Project is dependent on grant funding for the proposed Project. It is anticipated that the proposed Project would take approximately six months to construct.
Operation and Maintenance
The City would operate and maintain the new pipeline. Operations of the pipeline would be similar to its existing operations and maintenance (O&M) for City existing mains, consisting of standard, routine maintenance and inspections. These would be expected to be on as-needed basis.
Contact Information
Name
Dusty Duley
Agency Name
City of Willits
Job Title
Community Development Director
Contact Types
Lead/Public Agency / Project Applicant
Phone
Email
Name
Briza Grace Sholars
Agency Name
Provost & Pritchard Consulting Group
Job Title
Principal Environmental Planner
Contact Types
Consulting Firm
Address
Phone
Email
Location
Coordinates
Cities
Willits
Counties
Mendocino
Regions
Northern California
Cross Streets
County ROW along North Main Street in the City of Willits
Zip
95490
Total Acres
13.3
State Highways
Hwy 101
Waterways
Upp Creek
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Conservation (DOC), California Department of Fish and Wildlife, Northern and Eureka Region 1 (CDFW), California Department of Forestry and Fire Protection (CAL FIRE), California Department of Parks and Recreation, California Department of Toxic Substances Control (DTSC), California Department of Transportation, District 1 (DOT), California Department of Transportation, Division of Aeronautics (DOT), California Department of Transportation, Division of Transportation Planning (DOT), California Department of Water Resources (DWR), California Fish and Game Commission (CDFGC), California Highway Patrol (CHP), California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, North Coast Region 1 (RWQCB), California State Coastal Conservancy (SCC), California State Lands Commission (SLC), Office of Historic Preservation, State Water Resources Control Board, Division of Drinking Water, State Water Resources Control Board, Division of Drinking Water, District 3, State Water Resources Control Board, Division of Water Quality, State Water Resources Control Board, Divison of Financial Assistance
Development Types
Other (Pipeline Extension)
Local Actions
Pipeline Extension
Project Issues
Biological Resources, Cultural Resources, Tribal Cultural Resources
Public Review Period Start
Public Review Period End
Attachments
Draft Environmental Document [Draft IS, NOI_NOA_Public notices, OPR Summary Form, Appx,]
Notice of Completion [NOC] Transmittal form
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.