Bernell Hydraulics Property Removal Action Workplan
Summary
SCH Number
2026100062
Public Agency
California Department of Toxic Substances Control
(DTSC)
Document Title
Bernell Hydraulics Property Removal Action Workplan
Document Type
NOE - Notice of Exemption
Received
Posted
10/2/2026
Document Description
The project consists of implementing the Bernell Hydraulics Removal Action Workplan (RAW) to address elevated levels of total petroleum hydrocarbons - diesel range organics (TPH-DRO), lead, mercury, and polychlorinated biphenyls (PCBs) in soil at 8810 Etiwanda Avenue (Project Site) in the City of Rancho Cucamonga. The remediation consists of soil excavation and off-site disposal of approximately 138 cubic yards (cy) of contaminated soil and the recordation of a Land Use Covenant (LUC) restricting future use to commercial and industrial purposes.
Background: The Project Site is approximately 0.75 acres and consists of a single parcel identified by the County of San Bernardino as Assessor’s Parcel Number (APN): 0229-131-07-0000. Based on a review of historical documentation, the Project Site was initially developed as a California Department of Transportation maintenance yard by 1938. It operated as a metal recycling facility between 1970 and 1980, and later as a hydraulic systems fabrication, maintenance, and repair from the 1980s through August 2023. Currently, the Project Site is an unimproved, vacant parcel; all former buildings, ancillary structures, and concrete surfaces were demolished and removed early in October 2024. The Project Site is bordered by trucking facilities to the north and west, vacant lands to the south, and Etiwanda Avenue to the east. Bernell Hydraulics entered into a Voluntary Cleanup Agreement [Docket No. HSA-FY21/22-076, dated January 2022] with DTSC to oversee the investigation and remediation of hazardous substances at the Project Site.
Previous Investigations: In October 2021, a Phase I Environmental Site Assessment (ESA) was completed for the Project Site, identifying recognized environmental conditions (RECs) associated with historical site operations, heavy oil staining, and the potential for vapor encroachment. To further evaluate these impacts, a Supplemental Site Investigation (SSI) was conducted in 2025. The SSI identified elevated concentrations of TPH-DRO, lead, mercury, and PCBs in shallow soil. These concentrations exceed DTSC screening levels, necessitating the proposed removal action.
Project Activities: The RAW proposes excavating and disposing off-site of approximately 138 cubic yards of contaminated soil from three designated grid-squares: E-1 (20 cy impacted by TPH-DRO), D-2 (117 cy impacted by lead and mercury), and C-3 (1 cy impacted by PCBs-Arolclor 1254). Excavation will reach a maximum depth of 5.5 feet below ground surface (bgs). The excavated soil will be managed through a combination of direct loading into transport trucks and secure on-site staging. Staged soil will be covered with plastic sheeting during non-work hours to prevent wind dispersion and stormwater runoff. Off-site disposal of the excavated soil at licensed facilities (such as Soil Safe in Adelanto, CA; La Paz County Landfill, AZ; CWM in Kettleman Hills, CA; and US Ecology in Nevada) is estimated to require approximately 9 truck trips. Following the removal of contaminated soil, confirmation sampling will be conducted to verify that cleanup goals are achieved. Field activities are scheduled to be completed within 15 days.
Soil excavation activities will be permitted through the South Coast Air Quality Management District (SCAQMD). To comply with dust-suppression and stormwater-management requirements, all transport trucks and earth-moving equipment will undergo tire and exterior washing before leaving the Project Site to prevent the tracking of soil onto neighboring streets. Additionally, air quality will be monitored throughout the operation to verify that dust and contaminant vapors do not exceed levels of concern. These measures include conducting perimeter monitoring to confirm emissions do not migrate beyond the Site boundaries and applying foams or other vapor-control materials to suppress any present contaminant vapors.
Although not anticipated, in the event biological, cultural or historical resources are discovered in the course of project activities, work will be suspended while a qualified biologist, cultural or historical specialist makes an assessment of the area and arrangements are made to protect or preserve any resources that are discovered. If human remains are discovered, no further disturbance will occur in the location where the remains are found, and the County Coroner will be notified pursuant to the Health and Safety Code, Chapter 2, Section 7050.5.
Contact Information
Name
Mario Cazares
Agency Name
Department of Toxic Substances Control
Job Title
Senior Hazardous Substances Engineer
Contact Types
Lead/Public Agency
Phone
Name
Rhonda Garness
Agency Name
Jones Family Trust, Strack Family Trust
Job Title
Site Manager (Bernell Hydraulics)
Contact Types
Project Applicant
Phone
Email
Location
Coordinates
Cities
Rancho Cucamonga
Counties
San Bernardino
Regions
Southern California
Cross Streets
Etiwanda Avenue and Arrow Route
Zip
91739
Total Acres
0.75
Railways
Metrolink San Gabriel
Other Location Info
8810 Etiwanda Ave
Notice of Exemption
Exempt Status
Categorical Exemption
Type, Section or Code
Class 30, CCR Title 14, Sec. 15330
Reasons for Exemption
1. The project is a minor action designed to prevent, minimize, stabilize, mitigate or eliminate the release or threat of release of hazardous waste or hazardous substances.
2. The project is a removal action that will not exceed $1 million in cost.
3. The project will be consistent with applicable State and local environmental permitting requirements.
4. The project does not involve the onsite use of a hazardous waste incinerator or thermal treatment unit.
5. The project does not involve the relocation of residences or businesses.
6. The project does not involve the potential release into the air of volatile organic compounds as defined in Health and Safety Code Section 25123. (Exception: Small-scale in situ soil vapor extraction and treatment systems which have been permitted by the Air Pollution Control District or the Air Quality Management District.)
7. The exceptions pursuant to Cal. Code Regs., tit. 14, § 15300.2 have been addressed as follows:
a. Cumulative Impact. The project will not result in cumulative impacts because it is designed to be a short-term, final remedy that would not lead to a succession of projects of the same type in the same place over time.
b. Significant Effect. The environmental safeguards and monitoring procedures that are enforceable and made a condition of project approval will prevent unusual circumstances from occurring so that there is no possibility that the project will have a significant effect on the environment.
c. Scenic Highways. The project will not damage scenic resources, including but not limited to, trees, historic buildings, rock outcroppings, or similar resources, because it is not located within view of a highway officially designated as a state scenic highway.
d. Hazardous Waste Sites. The project is not located on a site which is included on any list compiled pursuant to Section 65962.5 of the Government Code.
e. Historical Resources. The project is not expected to cause a substantial adverse change in the significance of a historical resource because none are anticipated.
County Clerk
San Bernardino
Attachments
Notice of Exemption
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.