Oakmont Memorial Park Regulator Replacement Project

Summary

SCH Number
2026080480
Public Agency
East Bay Municipal Utility District (EBMUD)
Document Title
Oakmont Memorial Park Regulator Replacement Project
Document Type
NOE - Notice of Exemption
Received
Posted
8/14/2026
Document Description
The project involves the construction of a new regulator facility and associated pipeline, valves, and supporting infrastructure and demolition of the existing temporary regulator and associated pipeline, valves, and supporting infrastructure. Overview and Background The Colorados Pressure Zone Improvements Study (2021) identified the Oakmont Memorial Park Regulator as a critical facility for maintaining adequate fire flow capacity in the northern portion of the Leland Pressure Zone and recommended replacing the existing standby regulator with a permanent facility. The Oakmont Memorial Park Regulator Replacement Project (Project) involves constructing a new permanent facility and associated pipelines, valves and supporting infrastructure to replace the existing temporary regulator. Project Purpose and Objectives The purpose of this Project is to improve the regulator reliability through the construction of a permanent replacement facility. Project Location The Project is located within the public right-of-way along Reliez Valley Road in Pleasant Hill, as shown in Figure 1. Project Characteristics The Project consists of constructing a new regulator and the associated pipelines to supply the facility from the Colorados PZ. Once the new facility is operational, the existing regulator will be removed from service and demolished. Permits and Approvals A standard encroachment permit will be required to perform work within the public right-of-way along Reliez Valley Road. Any necessary permits from the regulatory agencies and jurisdictions will be obtained to complete the Project. Schedule and Work Hours The construction is anticipated to start in 2029 and will take approximately one year to complete. Construction activities will be limited to the daytime weekday hours (7:00 a.m. to 7:00 p.m.) to the extent feasible. EBMUD Practices and Procedures Standard construction environmental and safety practices applicable to all EBMUD construction projects have been incorporated into the Project. These standard practices minimize impacts to the public resulting from EBMUD construction projects.

Contact Information

Name
Charles Njoroge
Agency Name
East Bay Municipal Utility District
Job Title
Assistant Engineer
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project

Location

Cities
Pleasant Hill
Counties
Contra Costa
Regions
Northern California, San Francisco Bay Area
Cross Streets
Location 1: 160’ northwest of Reliez Valley Rd and Silverhill Dr
Zip
94523
Total Acres
0
Parcel #
Public Right of Way
State Highways
N/A
Railways
N/A
Airports
N/A
Schools
Pleasant Hill Adventist Academy
Waterways
Grayson Creek
Township
T01N
Range
R02W
Section
8
Base
N/A
Other Location Info
Coordinates: Location 1 (37°56'59.38"N 122°6'0.55"W), Location 2 (37°56'52.45"N 122°5'55.21"W) Cross Streets: Location 1 (160’ northwest of Reliez Valley Road and Silverhill Drive), Location 2 (20’ north of Reliez Valley Road and Grayson Road) Parcel #: Location 1 and 2 (Public Right of Way) Additional Schools: Christ the King Catholic School, Strandwood Elementary School, Sequioa Elementary School, Sequioa Middle School, Valley View Middle School, Valhalla Elementary School, Pleasant Hill Elementary School, Pleasant Hill Middle School Base: Walnut Creek

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
15301
Reasons for Exemption
The project is exempt under State CEQA Guidelines Section 15301 (Class 1) because it involves demolition of an existing temporary facility and 15303 (Class 3) because it involves the construction and installation of a new, small accessory facility and associated infrastructure. The project will not result in significant environmental effects related to its location, cumulative impacts, unusual circumstances, hazardous waste sites, or historical resources.

Exempt Status
Categorical Exemption
Type, Section or Code
15303
Reasons for Exemption
The project is exempt under State CEQA Guidelines Section 15301 (Class 1) because it involves demolition of an existing temporary facility and 15303 (Class 3) because it involves the construction and installation of a new, small accessory facility and associated infrastructure. The project will not result in significant environmental effects related to its location, cumulative impacts, unusual circumstances, hazardous waste sites, or historical resources.
County Clerk
Contra Costa

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.