Northtown Backup Generating Facility
Summary
SCH Number
2026070839
Lead Agency
California Energy Commission
Document Title
Northtown Backup Generating Facility
Document Type
NOP - Notice of Preparation of a Draft EIR
Received
Present Land Use
Combined industrial/commercial and industrial park
Document Description
The Northtown Backup Generating Facility (NTBGF) would consist of a total of forty two (42) diesel-fired generators that would be used exclusively to provide up to 97.3 megawatts (mw) of backup emergency generation to support Northtown Data Center (NTDC) to provide uninterrupted power for its tenants servers. The proposed project site is at the southwest corner of the intersection of West Trimble Road and Orchard Parkway in San José, California. The data center buildings, emergency backup generating facilities, project substation, water storage and treatment area, the PG&E; switching station, site circulation, and parking would be located on APNS 101-02-018 and 101-02-021. The entire project site is
approximately 28.5 acres. The NTBGF would only provide interconnection to the NTDC and would not be interconnected to the transmission or distribution grid. The project would construct a new 115-34.5 kilovolt (kv), 110 mega volt-ampere (mva) electrical substation (project substation) adjacent to the
proposed expansion of the recently permitted PG&E; utility. The two-bay project substation (two 105 mva 115kv - 34.5 kv step-down transformers and primary distribution switchgear) would be designed to allow one of the two transformers to be taken out of service, effectively providing 105 mva of total
power (a 2-to-make-1 design) of the 42 total generators, two of the generators would each have a generating capacity of up to 1.75 mw and the remaining 40 generators would each have a generating capacity of 3 mw. Of those 40 generators rated 3 mw, eight would be redundant. The generators would
be arranged in two generation yards located adjacent to each data center building (DC North and DC West). All 40 of the 3-mw generators would be dedicated to replacing the electricity needs of the data center in case of a loss of utility power, while the two 1.75-mw generators would be used to support
general office loads along with building and life safety services (i.e., house generators) during emergencies.
Contact Information
Name
Elizabeth Huber
Agency Name
California Energy Commission
Job Title
Project Manager
Contact Types
Lead/Public Agency
Phone
Name
Ward Mace
Agency Name
GIC San Jose LLC
Job Title
Regional Director
Contact Types
Project Applicant
Phone
Email
Location
Coordinates
Cities
San Jose
Counties
Santa Clara
Regions
Citywide
Cross Streets
West Trimble Road and Orchard Parkway
Zip
95131
Total Acres
28.5
Parcel #
101-02-018 and 101-02-021
State Highways
82,87,880,101
Railways
Peninsula, Coast, Warm Spring
Airports
SJC
Schools
San Jose Conservation Corps Charter, Orchard Elementary, Walter
Waterways
San Tomas Aquino Creek, Coyote Creek, Guadalupe River
Township
6S
Range
1W
Section
26
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Air Resources Board (ARB), California Department of Conservation (DOC), California Department of Fish and Wildlife, Bay Delta Region 3 (CDFW), California Department of Forestry and Fire Protection (CAL FIRE), California Department of Parks and Recreation, California Department of Toxic Substances Control (DTSC), California Department of Transportation, District 4 (DOT), California Department of Transportation, Division of Aeronautics (DOT), California Department of Transportation, Division of Transportation Planning (DOT), California Department of Water Resources (DWR), California Energy Commission, California Fish and Game Commission (CDFGC), California Governor's Office of Emergency Services (OES), California Highway Patrol (CHP), California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, San Francisco Bay Region 2 (RWQCB), Office of Historic Preservation, State Water Resources Control Board, Division of Drinking Water, State Water Resources Control Board, Division of Water Quality, State Water Resources Control Board, Division of Water Rights
Development Types
Power:Other Power Type (Backup Generating Facility)(Megawatts 97.3)
Local Actions
Specific Plan
Project Issues
Aesthetics, Agriculture and Forestry Resources, Air Quality, Biological Resources, Cultural Resources, Cumulative Effects, Drainage/Absorption, Economics/Jobs, Energy, Flood Plain/Flooding, Geology/Soils, Greenhouse Gas Emissions, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Mineral Resources, Noise, Population/Housing, Public Services, Recreation, Solid Waste, Transportation, Tribal Cultural Resources, Utilities/Service Systems, Wetland/Riparian, Wildfire
Public Review Period Start
Public Review Period End
Attachments
Draft Environmental Document [Draft IS, NOI_NOA_Public notices, OPR Summary Form, Appx,]
Notice of Completion [NOC] Transmittal form
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.