El Monte Pipeline No. 2

3 Documents in Project

Summary

SCH Number
2026060425
Lead Agency
City of San Diego
Document Title
El Monte Pipeline No. 2
Document Type
NOD - Notice of Determination
Received
Posted
10/2/2026
Document Description
The project proposes rehabilitation and repairs along 12.2 miles of the existing El Monte Pipeline, including the Grossmont Tunnel. The purpose of the rehabilitation is to extend the pipeline’s service life, enhance operational efficiency, and improve reliability. Improvements are proposed at approximately 69 locations comprising 1.35 acres along the existing pipeline, including improvements to and reconstruction of existing appurtenances, such as air valves, blowoffs, and access structures; installation of new isolation valves; and open trench replacement of approximately 450 feet of deteriorated pipeline along El Monte Road. The project would also include repairs to curb and gutter, sidewalks, and Americans with Disabilities Act (ADA) ramps at affected intersections, the repair of ornamental landscape in previously developed areas and native plant revegetation in open space areas. The pipeline alignment is located in the cities of Santee, La Mesa, El Cajon, and San Diego and the unincorporated community of Lakeside. The project is approximately 12.2 miles long and extends from near Lake Jennings in the northeast to the Alvarado Water Treatment Plant at Lake Murray in the southwest (Navajo Community Planning Area, Council District 7). WBS Number: S-10008.02.06

Contact Information

Name
Ramesis Bustamente
Agency Name
City of San Diego
Job Title
Associate Engineer
Contact Types
Lead/Public Agency

Location

Cities
El Cajon, La Mesa, San Diego, Santee, SD County (unincorporated Lakeside)
Counties
San Diego
Regions
Southern California
Other Location Info
SD County (unincorporated Lakeside), Cities of El Cajon, Santee, La Mesa, and San Diego

Notice of Determination

Approving Agency
City of San Diego
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Diego
Final Environmental Document Available at
https://www.sandiego.gov/ceqa/final

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.