Randall-Bold Water Treatment Plant Clearwell, Chemical Feed, and Sedimentation Basin Improvements Project

Summary

SCH Number
2026030820
Public Agency
Contra Costa Water District
Document Title
Randall-Bold Water Treatment Plant Clearwell, Chemical Feed, and Sedimentation Basin Improvements Project
Document Type
NOE - Notice of Exemption
Received
Posted
3/19/2026
Document Description
The purpose of this Project is to make safety and functionality improvements to the clearwell hydraulics system, chemical feed system, and the two sedimentation basins at CCWD’s Randall-Bold Water Treatment Plant in Oakley, CA. The current clearwell piping system is aging, and improvements are needed to improve system hydraulics, reduce health and safety risks, and ensure that the facility water treatment systems are effective. Piping within the clearwell hydraulics system will be replaced to improve system hydraulics, and bypass piping will be installed from CCWD’s multi-purpose pipeline (MPP) to Diablo Water District (DWD) to provide sufficient flow to DWD during the RBWTP’s annual shutdown period. Improvements within the sedimentation basins will include replacing aging sludge collection equipment, resurfacing eroded concrete launder surfaces, installing new overflow drain valves to improve basin drainage, and creating a safer access route through the installation of new stairways into the basins. Improvements to the chemical feed system will include replacing aging components throughout the system, including control panels, chemical feed piping, and obsolete sulfuric acid metering pump motors. Construction will occur between July 2026 and March 2028, with the majority of construction activities occurring during the RBWTP’s annual shutdown periods between October and December of 2026 and 2027, whereas clearwell bypass installation and testing will occur outside of these shutdown periods. Equipment laydown and vehicle staging will occur in a previously disturbed area adjacent to the work area within the boundaries of the RBWTP (see Figure 2).

Contact Information

Name
Cody Ericksen
Agency Name
Contra Costa Water District
Job Title
Associate Planner
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project

Location

Cities
Oakley
Counties
Contra Costa
Regions
Citywide
Zip
94561
State Highways
SR-4, SR-160
Railways
Amtrak, BART
Schools
Almond Grove Elementary, Freedom High School, Laurel Elementary
Waterways
East Antioch Creek, Contra Costa Canal, Tributary of East Antioch Creek
Other Location Info
The Randall-Bold Water Treatment Plant Clearwell, Chemical Feed, and Sedimentation Basin Improvements Project (Project) is located at Contra Costa Water District’s (CCWD) Randall-Bold Water Treatment Plant (RBWTP) at 3760 Neroly Road, Oakley, CA 94561. See Figure 1 for a Project vicinity map and Figure 2 for a Project location map.

Notice of Exemption

Exempt Status
Categorical Exemption
Type, Section or Code
Class 2, Section 15302 (c), and Class 1, Section 15301 (b)
Reasons for Exemption
This project is exempt under Class 2, Section 15302 (c), “replacement or reconstruction of existing utility systems and/or facilities involving negligible or no expansion of capacity”. This project is also exempt under Class 1, Section 15301 (b), as it involves the repair and maintenance of an existing facility owned by a public utility.
County Clerk
Contra Costa

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.