Talley Recharge Project
2 Documents in Project
Summary
SCH Number
2026030613
Lead Agency
Madera County
Document Title
Talley Recharge Project
Document Type
NOD - Notice of Determination
Received
Posted
9/29/2026
Document Description
The Project would construct a new point of diversion and intake/fish screen structure on the Eastside Bypass, a pump station, and an approximately 3,400-foot conveyance pipeline to divert flood flows to a dedicated 5-acre recharge basin and to approximately 160 acres of farmland for the purposes of groundwater recharge when flood waters area available. The Project is located in western Madera County west of State Route 99 and south of State Route 15, and is more particularly located on the north side of Avenue 18 1/2 between the Chowchilla Canal and the Eastside Bypass within assessor parcel numbers (APNs) 021-130-004 and 021-140-019.
Contact Information
Name
Trevor Stearns
Agency Name
Madera County
Job Title
Senior Planner
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Madera
Counties
Madera
Regions
Southern California, Unincorporated
Cross Streets
Avenue 18 1/2 / Road 8
Zip
93610
Total Acres
165
Parcel #
021-130-004 and 021-140-019
State Highways
NA
Railways
NA
Airports
NA
Schools
NA
Waterways
Eastside Bypass / Ash Slough
Township
10S
Range
14E
Section
34,35
Base
MDBM
Notice of Determination
Approving Agency
Madera County
Approving Agency Role
Lead Agency
Approved On
County Clerk
Madera
Final Environmental Document Available at
200 W. 4th Street, Suite 3100, Madera, CA 93637
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.