El Camino Real Widening Project, Arenal Road to La Costa Avenue
2 Documents in Project
Summary
SCH Number
2025100975
Lead Agency
City of Carlsbad
Document Title
El Camino Real Widening Project, Arenal Road to La Costa Avenue
Document Type
NOD - Notice of Determination
Received
Posted
11/16/2026
Document Description
(CIP 6051) This city project would widen and improve El Camino Real between Arenal Road and La Costa Avenue. Improvements, primarily on the street’s west side, include adding a third vehicle lane, installing full curb, gutter and sidewalk, installing street lighting and new landscaping, and installing stormwater improvements. The project would also construct new pedestrian bridges over San Marcos Creek and maintain existing buffered bikelanes. To transition to project improvements, restriping of part of El Camino Real north of Arenal Road would also occur. To accommodate project improvements, the project proposes right of way acquisition, an adjustment to a hardline preserve boundary of the city’s Habitat Management Plan and a waiver from General Plan open space boundary adjustment requirements.
Contact Information
Name
Brandon Miles
Agency Name
City of Carlsbad
Job Title
Associate Engineer
Contact Types
Lead/Public Agency / Project Applicant
Phone
Location
Cities
Carlsbad
Counties
San Diego
Regions
Southern California
Other Location Info
El Camino Real between Arenal Road and La Costa Avenue.
Notice of Determination
Approving Agency
City of Carlsbad
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Diego
Final Environmental Document Available at
www.carlsbadca.gov
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.