Yeager Well Replacement Project

Summary

SCH Number
2025070681
Lead Agency
State Water Resources Control Board
Document Title
Yeager Well Replacement Project
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
Single Residential (RS-10M)
Document Description
GSWC is planning to construct and operate replacement potable water supply well, Yeager Well 4, at its Yeager-Vale Plant. Yeager Well 2 will be decommissioned once Well 4 has been established. An adjacent GSWC-owned parcel to the south (APN: 058326107) has been identified by GSWC as the proposed location for the replacement well. The parcel is approximately 130 feet (east to west) by 100 feet (north to south). The addition of the parcel to the south would expand the total area of the Yeager-Vale Plant to approximately 0.77 acre. The Proposed Project would be part of GSWC’s Morongo Del Sur System, which delivers groundwater pumped from the Morongo Valley portion of the Morongo Basin located east and west of the Twenty-Nine Palms Highway between Morongo Valley and Yucca Valley. GSWC is proposing to decommission Yeager-2 once Yeager Well 4 has been established. Yeager-2 is approximately 300 feet deep, and the new Yeager-4 well would reach approximately the same depth. The facility would not require a crew or staff; therefore, no bathroom facilities would be built. The southern parcel, Parcel B, of the Project Site is undeveloped land, with mesquite dominated vegetation and cottonwood tree (Populus sp.) towards the eastern side, and overhead power lines parallel to the northern property line between the southern parcel and the Yeager-Vale Plant. The overhead power lines proceed north along the eastern perimeter of the Yeager-Vale Plant. As part of the construction, the vegetation and the large cottonwood tree will need to be removed and the ground leveled and prepared (i.e., temporary gravel bed) for heavy equipment prior to construction activities. The cottonwood tree measures 25 feet tall and has a 14.6-inch diameter at breast height (DBH). The Project ingress/egress would be on the western property boundary from Vale Drive (see Figure 3). The Yeager-Vale Plant has several permanent structures that would be protected in place: the Yeager-Vale Plant treatment building, generator, motor control center, and chemical building. The existing onsite discharge pond located on Parcel A would also remain in place. To manage excess water volumes generated during the well development phase that exceed the capacity of the existing discharge pond, a temporary above-ground high-capacity discharge pipeline would be installed. The line will extend east along Mojave Drive and then continue north along East Drive before terminating south of the East Drive and Covington Drive intersection, with the line discharging into an upland area (see Figure 3). The pipeline would span approximately 500 linear feet and be completely contained within the developed roadway and shoulder of Mojave Drive and East Drive. This alignment has been selected to avoid encroachment on wetland habitat within the Big Morongo Canyon Preserve. GSWC maintains regulatory coverage for this discharge under the State Water Board National Permit Discharge Elimination System (NPDES) Permit for Drinking Water System Discharges (Order No. WQ 2014-0194-DWQ, WDID No. 4DW0623), administered by the State Water Board Division of Water Quality. In June 2015, GSWC received a Notice of Applicability (NOA) for the Statewide Drinking Water System Discharge Permit, identification number 4DW0623, which asserts coverage under Order No. WQ 2014-0194-DWQ. Under this NOA, GSWC is authorized to discharge water from GSWC’s Morongo Del Sur Drinking Water system into the Big Morongo Creek (located within the Big Morongo Canyon Preserve). To ensure NPDES permit compliance, two temporary settling tanks would be deployed on Parcel B to remove suspended solids, reduce turbidity, and decrease flow velocity prior to discharge. These tanks operate based on gravitational sedimentation principles and serve as a best management practice for the discharge. The temporary discharge pipeline and settling infrastructure would be fully decommissioned and removed upon completion of construction activities. The highest pumping rate at Yeager-2 was 415 gallons per minute (gpm) when measured in 1990, and the pumping rate has declined nearly 50 percent in recent years. Yeager-4 is anticipated to have a capacity of 300-400 gpm. Pumping rates would be determined during drilling and are impacted by several factors including well interference at the well field, the nearby domestic wells across the street, and water quality. To meet the local noise ordinances, 24-foot-high sound walls would be required during well drilling. It is expected that the Project Site would need to be partially enclosed with sound walls strategically placed to minimize impacts to sensitive receptors to the west and south sides of the Project Site. Project construction, consisting of grading, well drilling, and equipping, would begin in August 2025 and take approximately five to six months to complete. Drilling would occur for approximately 150 days. Some components of the well drilling would require 24-hour operations.

Contact Information

Name
Wendy Pierce
Agency Name
State Water Resources Control Board
Job Title
Senior Environmental Scientist
Contact Types
Lead/Public Agency

Name
Omar Tinoco
Agency Name
Golden State Water Company-Barstow
Job Title
Associate Water Quality Engineer
Contact Types
Project Applicant

Location

Cities
Morongo Valley in unincorporated San Bernardino County
Counties
San Bernardino
Regions
Countywide
Cross Streets
11083 Vale Drive, at the intersection with Mojave Dr.
Parcel #
058326107 & 058326108
State Highways
62
Schools
Morongo Valley Elementary School

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
California Air Resources Board (ARB), California Coastal Commission (CCC), California Department of Conservation (DOC), California Department of Corrections and Rehabilitation (CDCR), California Department of Education, California Department of Fish and Wildlife, Cannabis Program (CDFW), California Department of Fish and Wildlife, Inland Deserts Region 6 (CDFW), California Department of Forestry and Fire Protection (CAL FIRE), California Department of Housing and Community Development (HCD), California Department of Parks and Recreation, California Department of Resources Recycling and Recovery, California Department of Toxic Substances Control (DTSC), California Department of Transportation, District 8 (DOT), California Department of Water Resources (DWR), California Energy Commission, California Fish and Game Commission (CDFGC), California Governor's Office of Emergency Services (OES), California Highway Patrol (CHP), California Native American Heritage Commission (NAHC), California Natural Resources Agency, California Office of Statewide Health Planning and Development (OSHPD), California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, Colorado River Basin Region 7 (RWQCB), California State Lands Commission (SLC), California Strategic Growth Council (SGC), Colorado River Board, Office of Historic Preservation, State Water Resources Control Board, Division of Drinking Water, State Water Resources Control Board, Division of Drinking Water, District 13, State Water Resources Control Board, Division of Drinking Water, District 27, State Water Resources Control Board, Division of Water Quality, State Water Resources Control Board, Division of Water Rights, State Water Resources Control Board, Divison of Financial Assistance
Development Types
Water Facilities (replacement)(Type Well, MGD 0.58)
Local Actions
None
Project Issues
Aesthetics, Agriculture and Forestry Resources, Air Quality, Biological Resources, Cultural Resources, Cumulative Effects, Drainage/Absorption, Energy, Flood Plain/Flooding, Geology/Soils, Greenhouse Gas Emissions, Growth Inducement, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Mandatory Findings of Significance, Mineral Resources, Noise, Population/Housing, Public Services, Recreation, Schools/Universities, Solid Waste, Transportation, Tribal Cultural Resources, Utilities/Service Systems, Vegetation, Wetland/Riparian, Wildfire
Public Review Period Start
Public Review Period End

Attachments

Notice of Completion [NOC] Transmittal form

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.

Download CSV Download All Attachments New Search Print