Calaveras Big Trees State Park - Big Trees Parkway Bridge Deck Replacement Project Bridge No. 30P-0001

3 Documents in Project

Summary

SCH Number
2025070612
Lead Agency
California Department of Parks and Recreation
Document Title
Calaveras Big Trees State Park - Big Trees Parkway Bridge Deck Replacement Project Bridge No. 30P-0001
Document Type
NOD - Notice of Determination
Received
Posted
2/17/2026
Document Description
The project would replace the deteriorated concrete roadway deck, walkway, and guardrail system at Big Trees Parkway bridge over the North Fork Stanislaus River in Calaveras Big Trees State Park. The proposed bridge would be 236 feet long and 36 feet wide, including barriers, two 13-foot-wide travel lanes, 2-foot-wide Manual for Assessing Safety Hardware (MASH)-compliant barriers on both sides of the bridge, and a 6-foot-wide sidewalk on the south side. The existing deck of the three-span bridge would be rehabilitated through deck replacement. The existing 4-foot-wide sidewalks located on the north and south sides of the bridge would be removed, and a new 6-foot-wide sidewalk on the south side of the bridge would be constructed. The project would also replace the existing timber guardrail with a new MASH-compliant guardrail.

Contact Information

Name
Joel Bonilla
Agency Name
California State Parks
Job Title
Environmental Coordinator
Contact Types
Lead/Public Agency

Location

Counties
Calaveras
Regions
Unincorporated
State Highways
Forest Rte 5N18
Other Information
The project is located at the bridge next to the Stanislaus RIver Access Day use area, within Calaveras Big Trees State Park.

Notice of Determination

Approving Agency
California State Parks
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.