New San Luis Obispo Courthouse Project

3 Documents in Project

Summary

SCH Number
2025050800
Lead Agency
Judicial Council of California
Document Title
New San Luis Obispo Courthouse Project
Document Type
NOD - Notice of Determination
Received
Posted
11/14/2025
Document Description
The Proposed Project would involve construction of a new approximately 145,000-square-foot, five-story, modern and secure courthouse to replace the existing Courthouse Annex building owned by San Luis Obispo County. The Proposed Project would consolidate court operations for court administrative staff offices that have been divided into off-site locations because of space limitations. The Proposed Project would involve demolition of two buildings and construction of a new 12-courtroom (four large courtrooms and eight multipurpose courtrooms) courthouse of approximately 145,000 square feet using a design-build delivery method. The project would include 17 secured parking spaces within the building: 15 for judicial officers and two for executive staff. Juror, public, and staff parking would continue to be available at the City's public parking garages, as currently being utilized for the existing downtown courthouse facilities.

Contact Information

Name
Kim Bobic
Agency Name
Judicial Council of California
Job Title
Senior Project Manager
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project

Name
Debra Lilly
Agency Name
Montrose Environmental
Job Title
Senior Environmental Professional
Contact Types
Lead/Public Agency

Location

Cities
San Luis Obispo
Counties
San Luis Obispo
Regions
Northern California
Cross Streets
Monterey Street and Toro Street
Zip
93401
Total Acres
1.43
Parcel #
002-326-021, 002-326-012
State Highways
Highway 1, US Highway 101
Railways
Southern Pacific
Airports
N/A
Schools
Hawthorne E.S., SLO Classical Academy H.S.
Waterways
San Luis Obispo Creek, Brizzolara Creek
Township
30 S
Range
12 E
Section
26
Base
SLO

Notice of Determination

Approving Agency
Judicial Council of California
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.

Download CSV Download All Attachments New Search Print