Finkbiner Park Multi-Benefit Stormwater Capture Project

2 Documents in Project

Summary

SCH Number
2024030529
Lead Agency
City of Glendora
Document Title
Finkbiner Park Multi-Benefit Stormwater Capture Project
Document Type
NOD - Notice of Determination
Received
Posted
1/30/2026
Document Description
The Project would construct a regional stormwater runoff capture facility within Finkbiner Park to provide multiple benefits including improved flood control, water quality, and water supply. The facility would involve diverting runoff from two adjacent drainage features into an underground capture, treatment, and infiltration facility situated beneath the existing ballfields. The Project represents an opportunity to implement regional-scale pollutant load reductions from a sizeable drainage area in the USGR Watershed as well as increase infiltration to the underlying groundwater aquifer. The Project would also include in-kind replacement of existing facilities within the site that require demolition to implement the stormwater BMP with new recreation facilities and features; conversion of the alley along the northern site boundary into a green alley through installation of permeable pavement; and installation of a recirculating stream, native landscaping, and adjacent path in the southeast portion of the site as a new passive recreation opportunity in the park.

Contact Information

Name
Maliha Fatima Ansari
Agency Name
City of Glendora
Job Title
P.E.
Contact Types
Lead/Public Agency / Project Applicant / Parties Undertaking Project

Location

Cities
Glendora
Counties
Los Angeles
Regions
Citywide
Cross Streets
North Minnesota Avenue & East Dalton Avenue
Zip
91741
Total Acres
3.8

Notice of Determination

Approving Agency
City of Glendora
Approving Agency Role
Lead Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
https://www.cityofglendora.org/businesses/public-notices

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.