Santa Venetia Floodwall Project

5 Documents in Project

Summary

SCH Number
2019079013
Lead Agency
Marin County Flood Control and Water Conservation District
Document Title
Santa Venetia Floodwall Project
Document Type
NOD - Notice of Determination
Received
Posted
10/22/2026
Document Description
The Marin County Flood Control District (District) is proposing to construct a sheet pile floodwall along the top of the existing earthen levee, from 55 Meadow Drive, west of the Meadow Drive Bridge, to Pump Station 5, which is just east of 825 Vendola Drive. The total length of the floodwall would be about 7,800 feet, and the maximum width would be about 14 inches. The floodwall would be constructed of composite or steel sheet piles. At the seven locations where storm drain and sewer main outfalls pass beneath or over the levee, the Project would route the pipelines through the sheet pile wall and use a clay check dam or similar materials to provide continuous flood protection. The District’s objective for the Project is to provide protection for the Santa Venetia neighborhood from the 100-year flood for the 30-year design life of the Project.

Contact Information

Name
Robin Bartlett
Agency Name
Marin County Flood Control and Water Conservation District
Job Title
Principal Engineer
Contact Types
Lead/Public Agency

Location

Cities
San Rafael, Unincorporated area
Counties
Marin
Regions
Northern California, Unincorporated
Cross Streets
Meadow Drive and Vendola Drive
Zip
94903
Waterways
South Fork Gallinas Creek
Township
2N
Range
6W
Section
10, 16
Base
MDM
Other Location Info
Along the south bank of South Fork Gallinas Creek and an existing earthen levee from 55 Meadow Drive, west of the Meadow Drive Bridge, to Pump Station 5, just east of 825 Vendola Drive in unincorporated San Rafael, Marin County.

Notice of Determination

Approving Agency
Marin County Flood Control District Board
Approving Agency Role
Lead Agency
Approved On
County Clerk
Marin
Final Environmental Document Available at
3501 Civic Center Drive, Suite 304, San Rafael, CA 94903

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Supplemental Environmental Review and Subsequent Mitigated Negative Declaration)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.

Download CSV New Search Print