Addendum to the Berths 212-224 [YTI] Container Terminal Improvements Project Environmental Impact Report

6 Documents in Project

Summary

SCH Number
2013041017
Lead Agency
Port of Los Angeles
Document Title
Addendum to the Berths 212-224 [YTI] Container Terminal Improvements Project Environmental Impact Report
Document Type
NOD - Notice of Determination
Received
Posted
8/27/2026
Document Description
The Addendum would issue a permit amendment with a term of up to 31 years to allow for continued operations of an existing marine container terminal and for YTI to complete the remaining components of the previous approved Environmental Impact Report (EIR). It would also modify the Mitigation Monitoring and Reporting Program (MMRP) into the permit amendment, which modifies the timing, updates the environmental requirements consistent with the 2017 Clean Air Action Plan update and applicable federal, state, and regional/local rules and regulations, and changes the name of the shipping company in lease measures contained in the MMRP. No new significant environmental impacts or substantial increase in the severity of previously identified significant effects have been identified from these Project modifications.

Contact Information

Name
Celia Sanchez Zelaya
Agency Name
Port of Los Angeles
Job Title
Assistant Planner
Contact Types
Lead/Public Agency

Location

Cities
Los Angeles
Counties
Los Angeles
Regions
Southern California
Cross Streets
New Dock Street & Pier S Avenue
Zip
90731
Other Location Info
Berths 212-224

Notice of Determination

Approving Agency
Los Angeles Harbor Department
Approving Agency Role
Lead Agency
Approved On
County Clerk
Los Angeles
Final Environmental Document Available at
https://www.portoflosangeles.org/environment/environmental-documents

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Addendum)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.