City of South San Francisco, Wet Weather management Project Phases 1, 2, 3, and 4
    3 Documents in Project
    
        
            
        
            
        
            
        
            
        
            
                
            
        
            
                
                    
                
        
            
    
    
            
                
                    
                
                    
                
                    
                    
                                    
                        
                
            
        
    
                    
                
            
                
            
                
            
                
            
                
            
                
            
                
    
        
        
            
                
                    
                    
                        
                                    
                        
                            
                        
                    
                            
        
        
            
                    
                        
                    
                        
                    
                        
                    
                        
                    
                        
                    
                        
                    
                        
                    
                        
            
        
    
                Summary
                SCH Number
            
            
                2002072064
            
        
                    Lead Agency
            
            
                City of South San Francisco
                
            
        
                Document Title
            
            City of South San Francisco, Wet Weather management Project Phases 1, 2, 3, and 4
        
                Document Type
            
            
                NOD - Notice of Determination
            
        
                Received
            
            
                    Posted
                
                
                    12/13/2002
                
            
                    Present Land Use
                
                
                    Primary Light Industrial and Office
                
            
                Document Description
            
            The proposed project consists of four phases as follows;
1.  Phase 1 is to construct pump station improvements, parallel force mains, and an effluent storage pond;
2.  Phase 2 is to construct new replacement sewers and rehabilitate deteriorated sewers;
3.  Phase 3 is to construct the protection system to prevent further erosion of the Colma Creek bank at the Water Pollution Control Plant; and
4.  Phase 4 is to construct relief sewers and to rehabilitate deteriorated sewers.
        Contact Information
                        Name
                    
                    
                        James Hockenberry
                    
                
                        Agency Name
                    
                    
                        State Water Resources Control Board
                    
                
                        Contact Types
                    
                    
                        Lead/Public Agency
                    
                
                            Phone
                        
                        
                    Location
                    Cities
                
                San Francisco
            
                    Counties
                
                San Francisco
            
                    Cross Streets
                
                
                    Varies
                
            
                    State Highways
                
                
                    101/ 380
                
            
                    Railways
                
                
                    UP
                
            
                    Airports
                
                
                    SFO
                
            
                    Waterways
                
                
                    SF Bay, Colma Creek
                
            Notice of Determination
                        Approving Agency
                    
                    
                        State Water Resources Control Board                             
                    
                
                            Approving Agency Role
                        
                        
                            Responsible Agency
                        
                    
                            Approved On
                        
                        Determinations
                            (1) The project will have a significant impact on the environment
                        
                        
                            No
                        
                    
                            (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
                        
                        
                            No
                        
                    
                            (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
                        
                        
                            Yes
                        
                    
                            (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
                        
                        
                            No
                        
                    
                            (3) Mitigated measures were made a condition of the approval of the project
                        
                        
                            No
                        
                    
                            (4) A mitigation reporting or monitoring plan was adopted for this project
                        
                        
                            N/A
                        
                    
                            (5) A Statement of Overriding Considerations was adopted for this project
                        
                        
                            No
                        
                    
                            (6) Findings were made pursuant to the provisions of CEQA
                        
                        
                            N/A
                        