USS-UPI, LLC., formerly USS-Posco Industries, Post Closure Hazardous Waste Facility Permit Renewal
4 Documents in Project
Summary
SCH Number
2002062026
Lead Agency
California Department of Toxic Substances Control
(DTSC)
Document Title
USS-UPI, LLC., formerly USS-Posco Industries, Post Closure Hazardous Waste Facility Permit Renewal
Document Type
NOD - Notice of Determination
Received
Posted
9/9/2025
Document Description
The California Department of Toxic Substances Control (DTSC), pursuant to authority granted under California Code of Regulations, Title 22, Division 4.5, Chapter 20 is approving an addendum to a previously adopted Mitigated Negative Declaration for the renewal of a Post Closure Hazardous Waste Facility Permit (Permit) for USS-UPI, LLC (Facility), formerly USS-Posco Industries, for ten years. This Permit will allow continued post closure maintenance of the hazardous waste landfill, Unit 1 Corrective Action Management Unit (CAMU). This Permit Renewal does not include any changes in operations or construction, and there are no proposed ground disturbing activities.
Contact Information
Name
Elly Daoud
Agency Name
Department of Toxic Substances Control
Job Title
Hazardous Substances Engineer
Contact Types
Lead/Public Agency
Phone
Email
Name
Markus Boro
Agency Name
USS-UPI, LLC., formerly USS-Posco Industries
Job Title
Plant Manager
Contact Types
Project Applicant
Phone
Email
Location
Cities
Pittsburg
Counties
Contra Costa
Regions
San Francisco Bay Area
Other Location Info
900 Loveridge Road, Pittsburg, CA 94565
Notice of Determination
Approving Agency
Department of Toxic Substances Control
Approving Agency Role
Lead Agency
Approved On
County Clerk
Contra Costa
Final Environmental Document Available at
Department of Toxic Substances Control;
Permitting Division;
8800 Cal Center Drive;
Sacramento, CA 95826
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.