POWER LINE ROAD PHASE 2 (PLR2/ER-1)
20 Documents in Project
Summary
SCH Number
1992032074
Lead Agency
Sacramento County
Document Title
POWER LINE ROAD PHASE 2 (PLR2/ER-1)
Document Type
NOD - Notice of Determination
Received
Posted
1/15/2026
Document Description
The project consists of planned widening Power Line Road from a two-lane local road to a two-lane arterial with a center turn lane. Widening will occur from the intersection of Power Line Road at Allbaugh Drive to West W Elverta Road and 2,100 linear feet (0.4 miles) along West W Elverta Road. The project will include a potable water line and storm drain improvements to accommodate the road widening . A total of twenty utility poles will be relocated by Sacramento Municipal Utility District (SMUD) along Power Line Road and W Elverta Road. Seven poles located east of the Power Line Road/ W Elverta Road intersection will be relocated south approximately 30 feet from the existing pole locations. Thirteen poles located south of the Power Line Road/W Elverta Road will be relocated approximately 75 feet from the E3xisting pole locations. The total length of the project is approximately 4,900 linear feet.
Contact Information
Name
Julie Newton
Agency Name
Sacramento County
Job Title
Environmental Coordinator
Contact Types
Lead/Public Agency
Phone
Email
Name
Nestor Hernandez
Agency Name
Sacramento County Department of Transportation
Job Title
Project Engineer
Contact Types
Project Applicant / Parties Undertaking Project
Phone
Location
Cities
Sacramento
Counties
Sacramento
Regions
Countywide, Unincorporated
Parcel #
201-1020-006,201-1020-095,201-1020-057,201-0160-046,201-0130-034 ,201-1020-057,201-1020-059
Other Location Info
The project site is located in Metro Air Park, on Power Line Road, from Allbaugh Drive to West W Elverta Road and 2,100 feet east along West W Elverta Road.
Other Information
201-1020-098,201-0130-011 ,201-0130-029,201-1020-002,201-01 30-030
Notice of Determination
Approving Agency
County of Sacramento
Approving Agency Role
Lead Agency
Approved On
County Clerk
Sacramento
Final Environmental Document Available at
https://planningdocuments.saccounty.net/
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
Yes (Addendum)
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Attachments
Notice of Determination
Disclaimer: The Governor’s Office of Land Use and Climate Innovation (LCI) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit LCI’s Accessibility Site.